Sukkur Barrage Kotri barrage Guddu

Sectoral and Institutional Context

Pakistan’s agricultural sector is almost wholly dependent on irrigation: irrigated land supplies more than 90 percent of agricultural production. Agriculture in most areas is not possible without irrigation because the climate of Pakistan is arid to semi-arid with low and variable rainfall. Annual rainfall over much of the area is not more than 150 mm per annum with high evaporation rates, ranging from 1,250 mm to 2,800 mm per annum.

Given climate change and high population growth rates, current forms of water resources management are widely recognized as being unsustainable and inadequate to ensure future water availability for food security, economic growth, and the needs of the environment.

Barrages are strategic hydraulic assets. Barrages are used to raise the water level in the river so that irrigation water can be diverted to the main and link canals by gravity for various uses. Barrages are also used for river control and flood management, act as a source of water supply for all sectors of the economy, function as bridges over rivers, and are often used for utility crossings such as gas pipelines. Therefore, the condition and the safe and reliable operation of a barrage have far-reaching implications for the livelihood and economic growth of all segments of society.

 

Priorities for Improvement of Barrages in Sindh. Three large barrages were built between 1932 and 1962 on the Indus River in Sindh province. The northern one, Guddu Barrage, has developed major safety issues. The second one, Sukkur barrage, is one of the oldest and serves about 3 million hectares of agricultural lands. Over the decades, it has also developed safety issues. Repairs on the Sukkur Barrage are being carried out regularly. The last one (most southerly), the Kotri Barrage, was rehabilitated in 2000.

The project area is dry with a mean annual rainfall of less than 88 mm. There are two wet seasons: the first with low rainfall in February and March and second with higher rainfall in the monsoon period of July, August, and September. About 80% of the mean annual rainfall occurs in the two wet seasons.

 

Guddu barrage. The primary function of the gated Guddu barrage is to provide irrigation water to over one million hectares of agricultural lands in the Jacobabad, Larkana and Sukkur districts of Sindh and the Naseerabad district of Balochistan, by feeding the Ghotki Feeder and Rainee canals on the left (east) side and the Begari Sindh (BS) Feeder and Desert Pat Feeder canals on the right (west) side. The barrage incorporates two fish ladders. The barrage is also used for river control and flood management. It has been designed to pass a super-flood discharge of up to 33,980 cubic meters per seconds (m3/sec). The barrage is also an important transport link across the River Indus and provides cooling water for the thermal power station at Guddu. Two major gas lines cross the barrage. The barrage was commissioned in 1962 and has now seen over fifty years of active service. It consists of 64 gates of 18 meters each and one navigation lock with a span of 15 meters. The gates weighing 55 to 100 tons are “fixed wheel” type and operate without counterweights.

 

Rehabilitation and modernization of Guddu barrage is needed. A recently completed feasibility study an international engineering consulting firm, which was commissioned by the Government of Sindh by, indicates that there are serious operational difficulties and safety issues, the most severe problems being: i) up to 60% of the steel of the 65 gates on the main barrage is badly corroded; ii) the lifting mechanisms are badly corroded, with a strong possibility of failure; iii) the switch panels and power distribution network are in extremely poor condition; and iv) there is no backup power supply system in case of power failures. Currently stress levels within the gates are already in excess of the allowable design stresses during normal operation. Since the rate of corrosion cannot be slowed it is considered likely that the gates will fail during normal operation within 5 years. There is already at risk now that the gates may fail in case of a flood event that necessitates opening and closing. Such a failure is likely to be catastrophic, affecting water supplies to all the irrigated areas supplied by the barrage Due to the recent flood events upstream embankments were breached. The embankments around the Guddu barrage require upgrading to meet the new criteria: they must be able to withstand 1:100 year floods.

Pakistan is already one of the most climate-vulnerable countries in the world due to its complex geography (e.g. high evaporation rate, monsoon influence, and glacier dynamics). Climate change is expected to increase the occurrence of extreme climatic events (such as floods), and the temporal and spatial availability of water. The expected changes in river discharge rate will alter the physical forces exerted on the barrage and pose risks to its operation, safety, and structural integrity. With the possibility of higher future flows due to climate change and increased retrogression, project interventions are even more vital to ensure the safety of the barrage. Recently the government has started to explore the combination of “hard” interventions (to protect high-value infrastructure such as barrages) and “soft” interventions (smart adaptation to living with floods), which have been used to considerable effect in countries as diverse as the United States and the Netherlands and are a globally-accepted best practice.

 

Institutional challenges and reform. Pakistan has a long- and well-established tradition of water entitlements. The 1991 Provincial Water Accord established clear entitlements for each province to surface waters. Implicit in the Water Accord is a set of water entitlements at the canal command level. In large areas of the system these entitlements serve as the basis for allocation of water among

canal commands. There are also well-established rules for further distributing water to the distributary canals and canal outlets. The water economy of Pakistan depends fundamentally on a gigantic hydraulic infrastructure system. The major challenge which has to be addressed is how to maintain what has been built. Many elements of the vast hydraulic system are now reaching the end of their design lives such as the Guddu barrage, and have to be rebuilt. The barrages are classic “public goods”, and as strategic assets would remain under public management even after the transformation of the irrigation system under the current reform program.

 

Relationship to CAS

14. The Bank’s Country Partnership Strategy (CPS) for 2010-14 emphasizes among other things the need for improving infrastructure to support growth (Pillar 3). Under Pillar 3, improved sustainability of water and irrigation systems contributes to the “sub-pillar” of strengthened irrigation infrastructure and agricultural competitiveness.